Project Work Breakdown Structure
(Team project)
Overview
The purpose of this Team assignment is to:
Determine the work required to build Mamma Mia’s IT system.
List all deliverable end items in the form of Summary Tasks.
Define and list sub-tasks under each Summary Task.
Produce a final WBS.
There are three parts to this assignment.
Part 1 – Team-reviewed Project Charter in Microsoft Word
In Week 2, each of your team members created a Project Charter. Your team needs only one Project
Charter. As a team, select one Charter to use for this assignment. Be sure to update it using the
assignment feedback from Week 2, the Case Study, and deliverable and task elements specified in Part 2
of this assignment. The Charter and the project WBS must align with each other.
IMPORTANT: The submission file should be named as “Group” “Team Name” “Deliverable for”
“Assignment Name”, such as – Group A Projecteers Charter for Project WBS.docx
Part 2 – Work Breakdown Structure in Microsoft Project
Re-read the following:
“How to Build Work Breakdown Structures” (Week 1 ? Reading), paying close attention to
o WBS Creation process
o Definitions
o Convention for WBS structure
o Considerations for building the WBS
o Schedule development process
o Naming Terminology
“What NOT to do in a WBS” (Week 1 ? Reading)
Before creating the WBS, open a blank project in Microsoft Project. Apply the settings from the Project
Configuration Settings section in “Project Tutorials” (Course Resources). As a team, develop and submit
a project work breakdown structure (WBS) in Microsoft Project’s .mpp format. Your WBS should include
all work necessary to complete the scope of the project, specifically including the technical IT work of
the project.
The WBS should include the project management effort as well. This is the work the Project Manager
(and team) must do to keep the project moving in the right direction. It would include such things as
team and customer meetings, briefs to the sponsor, status reports, and so on.
At this stage, the Project WBS should not include:
Duration estimates (just leave it at the “1d” default value)
Predecessor-successor links (aka dependencies)
Resource data (cost, names, etc.).
Project WBS Fall 2021
Page 1 of 6
Project Work Breakdown Structure
(Team project)
Here are some Level 2 WBS elements you should include (among others), not necessarily in the order
shown:
IT System Design
System Hardware
System Software
System Networking
System Test
Project Management
System Transition
With respect to hardware, software, and networking – lower level WBS elements will deal with Orders,
Delivery, Receiving, Installation, etc. Make sure that your WBS (and .mpp file) include the following tasks
as part of your WBS. These are necessary but more tasks may well be needed. This also does not mean
that a single task will necessarily suffice for each of these. Rather, include as many tasks as it takes to do
the job, but please include at least the following kinds of tasks in addition to whatever else you were
planning for your WBS:
Ordering, and receiving hardware
Ordering, and receiving software
Ordering, and receiving networking
Installing hardware
Installing software
Installing networking
Managing, controlling, and monitoring the project and the team
Project status reports
There is a lot more to the WBS than this. Do not spend too much time getting “down into the weeds”. A
good size for this class would be no more than 10 Level 2 elements. Decompose these to Level 3
elements (or Level 4 if absolutely necessary). Remember, the lowest level elements (those with indented
sub-tasks, not indented summary tasks) will be your work packages.
Finally, define and list sub-tasks within each work package.
Project WBS Fall 2021
Page 2 of 6
Project Work Breakdown Structure
(Team project)
Formatting Your Project WBS
Use the Insert Column function (read about this in “Project Tutorials” ? Show the Project WBS
Numbers) so the Project WBS shows the following columns (in this order):
Indicators (column shows
Task Mode
Constraint Type
Constraint Date
Outline Level
WBS
Task Name
Duration
Start
Finish
Predecessors
Successors
Type
)
IMPORTANT: The submission file should be named as “Group” “Team Name” “Deliverable for”
“Assignment Name”, such as – Group A Projecteers Project File for Project WBS.mpp
Project WBS Fall 2021
Page 3 of 6
Project Work Breakdown Structure
(Team project)
Part 3. Answers to Questions in Microsoft Word
Read and think through the options and alternatives suggested by these questions before you build your
Project WBS. When your Project WBS is completed, answer the following questions, and submit them as
a Microsoft Word document. “Yes” or “No” answers with no explanations or discussions are not
appropriate answers.
1. Does the Project Schedule include everything in your team’s charter and all deliverables? If the WBS
includes tasks that were not part of the Project Charter, explain how the team determined the
additional tasks were necessary.
2. Does the WBS include project management tasks necessary to manage the project?
3. Explain the top-down and bottom-up approaches to building a WBS. Which approach did the team
decide to use and why did they make that decision?
4. Building the WBS as an outline in Word or Excel instead of Project can help team members visualize
the order of the tasks and how the tasks might decompose into lower levels. Did the team build an
outline outside of Project? If you only used Project, did the team need to rearrange tasks while
building the WBS?
5. Did the team approach the WBS graphically (like an organization chart) or tabularly (like a list or
table), or something else? Why?
6. Did the team work together to determine the major tasks or was only one team member responsible
for that? How well did it work?
Project WBS Fall 2021
Page 4 of 6
Project Work Breakdown Structure
(Team project)
Formatting Your Questions Document
Create an APA format title page that includes: The title of report (Questions for Project WBS),
your name, Course and Section number and date (use assignment due date); do not include
graphics or themes.
No running header required for this document.
The body of the paper should be double (or 1.5″) spaced, and no longer than 5 pages.
Answers should be formatted as normal sentences (no numbering, not a run-on sentence as
part of the question, no indenting).
Use 1″ margins on all sides.
Font should be 11-point Calibri, 11-point Arial, 10-point Lucida Sans Unicode, 12-point Times
New Roman, 11-point Georgia, or 10-point Computer Modern.
Font should remain consistent throughout the paper, i.e., not changing from one font to
another.
Use at least one external reference and one from the course content (from the class reading
content, not the assignment instructions or case study itself) with APA formatted citation and
reference. For information on general APA format and specifics related to citing from the class
content, refer to Content ? Course Resources ? Writing Resources. Resources must not use
Wikipedia, general information sites, blogs, or discussion groups.
The list of References must be its own page at the end of the document and it must be in APA
format, i.e., double spaced, .5″ hanging indent. No more than 10% of the paper may be in the
form of a direct citation from an external source. All in-text citations must appear in the
References list and all entries in the References list must be used as in-text citations.
Run Microsoft Word’s grammar/spell checker; there should be no errors in grammar, verb
tenses, pronouns, spelling, punctuation, first person usage, or contractions.
Submit your paper as a Word document, or a document that can be read in Word.
IMPORTANT: The submission file should be named as “Group” “Team Name” “Deliverable for”
“Assignment Name”, such as – Group A Projecteers Questions for Project WBS.docx
Project WBS Fall 2021
Page 5 of 6
Project Work Breakdown Structure
(Team project)
Grading Rubric
90-100%
80-89%
70-79%
60-69%
< 60%
Far Above Standards
Above Standards
Meets Standards
Below Standards
Well Below Standards
Criteria
Team-reviewed Project Charter
5 Points
4 Points
Updated Charter revised to match
scope and WBS.
Scope and deliverables fully
updated and aligned with
WBS.
Scope and deliverables
mostly updated and aligned
with WBS.
Configuration Settings
Needed for producing consistent
results in the Project WBS.
Work Breakdown Structure
WBS is decomposed to Level 4,
uses Project's WBS numbering,
rows are continuous, includes
specified WBS elements, satisfies
scope of the Project Charter.
Schedule Structure
No durations, resources,
dependencies, or costs specified.
Includes Project Start and Project
Complete.
Schedule Details
Tasks describe work/deliverables
(not a checklist) using provided
naming conventions. 125 rows or
less, columns reveal specified
fields. No color-coding, special
characters, or task names with
full sentences.
Questions
Answers appropriately explain
concepts (not yes/no).
Research
Use at least 2 references from
academically credible sources
with APA formatted citation (intext).
Format
Uses format provided. Includes
Title Page and References Page.
Project WBS Fall 2021
5 Points
All configuration settings
correct.
3 Points
4 Points
Scope and deliverables
moderately updated and
aligned with WBS.
3 Points
Missed 1-2 configuration
settings.
Missed 3-4 configuration
settings.
2 Points
Scope and deliverables
somewhat updated and
aligned with WBS.
2 Points
Missed 4-5 configuration
settings.
0-1 Points
5
Scope and deliverables not
updated or aligned with
WBS.
0-1 Points
5
Missed 5 or more
configuration settings.
9-10 Points
8 Points
7 Points
6 Points
0-5 Points
Correctly decomposed the
schedule, no blank rows,
included all specified WBS
elements, all deliverables
align to the Project Charter.
Decomposed too little (Level
3), or too much (Level 5);
included a few more (or less)
than 10 Level 2 elements;
most of the specified lower
level elements, project
management elements,
and/or deliverables aligned
to the Project Charter.
Under-decomposition (Level
2), or over-decomposition
(Level 6); missing several of
the specified lower level
elements, project
management elements,
and/or deliverables aligned
to the Project Charter.
Too much decomposition
(beyond Level 6); only
includes some of the
specified lower level
elements, project
management elements,
and/or deliverables aligned
to the Project Charter.
No decomposition at all
(stopped at Level 1); left
blank rows in the schedule,
includes few of the specified
lower level elements, project
management elements,
and/or deliverables aligned
to the Project Charter.
18-20 Points
16-17 Points
14-15 Points
12-13 Points
0-11 Points
No durations, resources,
dependencies, or costs; First
task is Project Start
milestone, last task is
Project Complete milestone.
Applied some durations,
resources, dependencies, or
costs; Loaded most sub-task
durations and some
start/finish dates.
Applied several durations,
resources, dependencies, or
costs; Loaded several subtask durations but also
several start/finish dates.
Applied many durations,
resources, dependencies, or
costs; Loaded some subtask durations and MSProject calculates some
start/finish dates.
Applied durations, resources,
dependencies, and costs;
Loaded all sub-task
durations so MS-Project
cannot calculate start/finish
dates; First task is not
Project Start milestone, and
last task is not Project
Complete milestone.
18-20 Points
16-17 Points
14-15 Points
12-13 Points
0-11 Points
Row count is 125. All tasks
follow correct naming
convention, do not
encompass multiple
deliverables/actions, or use
full sentences. Color-coding
and special characters are
not used. Columns reveal all
specified fields.
Row count is a little over
125. 1-2 Tasks use incorrect
naming convention, use full
sentences as names, or
encompass multiple
deliverables/actions.
Columns reveal most
specified fields.
Row count is several more
than 125. 3-4 Tasks use
incorrect naming convention,
use full sentences as names,
or encompass multiple
deliverables/actions.
Columns reveal several
specified fields.
Row count is many more
than 125. 5-6 Tasks use
incorrect naming convention,
use full sentences as names,
or encompass multiple
deliverables/actions.
Columns reveal some
specified fields.
Row count is far more than
125. 7 or more Tasks use
incorrect naming convention,
use full sentences as names,
or encompass multiple
deliverables/actions.
Specified fields not revealed.
Color-coding or special
characters used. Tasks read
like a checklist.
18-20 Points
16-17 Points
14-15 Points
12-13 Points
0-11 Points
All questions answered with
appropriate explanations.
1 question not answered or
does not use appropriate
explanations.
2-3 questions not answered
or do not use appropriate
explanations.
4-5 questions not answered
or do not use appropriate
explanations.
Questions not answered or
do not use appropriate
explanations.
9-10 Points
8 Points
7 Points
6 Points
0-5 Points
Required references are
incorporated, used
effectively, and cited using
APA style. References used
are relevant and timely and
contribute strongly to the
analysis.
Required references are
relevant, and somewhat
support the analysis.
References are appropriately
incorporated and cited using
APA style.
Only one reference is used
and properly incorporated,
and/or reference(s) lack
correct APA style.
A reference may be used, but
is not properly incorporated
or used, and/or is not
effective or appropriate,
and/or does not follow APA
style for references and
citations.
No course content or
external research
incorporated, or reference
listed is not cited within the
text.
9-10 Points
8 Points
7 Points
6 Points
0-5 Points
Well organized and easy to
read. Very few or no errors in
sentence structure,
grammar, or spelling; doublespaced, written in third
person, and presented in a
professional format.
Effective organization. Has
few errors in sentence
structure, grammar, and
spelling; double-spaced,
written in third person, and
presented in a professional
format.
Some organization. May
have some errors in
sentence structure,
grammar, and spelling;
double spaced and written in
third person.
Not well organized, and/or
contains several errors in
grammar and/or spelling,
and/or is not double-spaced
and written in third person.
Extremely poorly written, has
many errors in grammar
and/or spelling, or does not
convey the information
required.
Page 6 of 6
Possible
Points
10
20
20
20
10
10
1
Project Charter (Individual project)
Student name
University
course
Professor
March 24, 2024
2
Executive Summary:
This project charter delineates the strategy to conceptualize, construct, and deploy an
information technology (IT) infrastructure for Mamma Mia's Bakery and Sandwich Shoppe. The
core objective is optimizing operational workflows, refining procedures, and introducing
contemporary features like point-of-sale systems, inventory monitoring, online ordering, and
payment processing capabilities. The project harmonizes with Mamma's aspiration to broaden
her enterprise and adapt to shifting customer preferences. Our methodology entails an intimate
partnership with Mamma to grasp her needs, elucidate IT intricacies, and furnish a seamless
solution (Noortman et al., 2022). This collaborative effort aims to propel Mamma's Bakery and
Sandwich Shoppe into a technologically adept and customer-centric establishment.
Project Scope:
The project scope encompasses the comprehensive design, development, and
implementation of an information technology (IT) system explicitly customized for Mamma Mia's
Bakery and Sandwich Shoppe. This includes the following key components:
Integration of a robust point-of-sale system to streamline transaction
processing and enhance customer checkout experience.
Implementation of advanced inventory management software to facilitate
efficient tracking, monitoring, and replenishment of bakery supplies and products.
Development of a user-friendly online ordering platform, including
website creation, to enable customers to place orders remotely and enhance accessibility.
Integration of secure payment processing capabilities to support various
payment methods and ensure seamless customer transactions. This scope delineates the
3
essential functionalities and features that will be incorporated into the IT system to
modernize operations and meet the evolving needs of Mamma Mia's Bakery and
Sandwich Shoppe.
Exclusions:
Networking infrastructure setup
LAN or internet installation
Comprehensive productivity software
Project Objectives:
1.
Implement a modern IT system to enhance operational efficiency:
?
Introduce cutting-edge technology solutions tailored to the
bakery's specific requirements.
?
Streamline internal processes and workflows to optimize
productivity and minimize manual tasks.
2.
Facilitate online ordering and payment processing for customers:
?
Develop a user-friendly online platform to enable customers to
place orders remotely.
?
Implement
secure
payment
processing
capabilities
to
accommodate various payment methods.
3.
Enable inventory management and tracking to streamline operations:
?
Integrate robust inventory management software to track and
manage bakery supplies effectively.
4
?
Implement automated inventory tracking mechanisms to prevent
stockouts and minimize wastage.
4.
Provide training and support to Mamma Mia and her team for effective
system utilization:
?
Conduct comprehensive training sessions to familiarize Mamma
Mia and her team with the new IT system.
?
Offer ongoing technical support and assistance to ensure smooth
adoption and utilization of the system.
Project Management Approach:
The project will follow a structured approach based on industry best practices (Bentley et
al., 2000), including:
Agile for iterative development and continuous feedback.
The project will follow an Agile methodology, which allows for iterative development and
continuous feedback loops. This method focuses on adaptability and responsiveness to changing
needs, progressively allowing the project team to produce value. Breaking the project into
digestible iterations or sprints enables the team to prioritize activities, address difficulties quickly,
and include stakeholder feedback throughout development. This iterative approach ensures that
the IT system evolves to Mamma Mia's changing needs and preferences, increasing the likelihood
of success.
5
Regular communication and collaboration with stakeholders.
Effective communication and engagement with stakeholders are critical for project
success. The project team will keep open lines of communication with Mamma Mia, key decisionmakers, end users, and other stakeholders. Regular meetings, status updates, and progress
reports will help to increase transparency and match expectations. By actively involving
stakeholders throughout the project lifecycle, the team may identify possible difficulties early on,
gain valuable insights, and ensure that the final deliverables fulfill stakeholders' needs and
objectives.
Adequate project documentation and milestone tracking ensure transparency,
accountability, and traceability. The project team will record all requirements, plans, timetables,
and progress. This paper acts as a reference point for all stakeholders and outlines a clear plan
for project implementation. Milestones will be developed and tracked to track progress, identify
dependencies, and compare performance to project goals. Regular review sessions will keep the
project on track and swiftly handle any deviations from the plan.
Continuous Risk Assessment and Mitigation Throughout the project lifecycle.
Risk management is critical for project success, especially in complicated endeavors like
IT system deployment. The project team will conduct risk assessments to identify potential
threats and opportunities. Risks will be classified, assessed, and prioritized according to their
significance and likelihood of occurrence. Mitigation plans will be devised and implemented to
address identified risks, reduce their impact, and seize potential opportunities. By proactively
managing risks throughout the project lifecycle, the team may mitigate uncertainties and boost
the possibility of attaining project objectives within the defined restrictions.
6
Technical Solution:
The IT system will comprise:
Point-of-Sale Software with Inventory Management Integration: Integrating point-of-sale (POS)
software with inventory management will transform Mamma Mia's Bakery's transaction
processing. This system will allow for seamless synchronization of sales and inventory, ensuring
that stock levels are automatically updated as things are sold. Staff will have real-time inventory
visibility, allowing for timely replenishing and reducing the likelihood of stockouts or
overstocking. Furthermore, proper inventory management improves order fulfillment and
reduces discrepancies in stock counts, resulting in increased operational efficiency and customer
satisfaction.
Customized Online Ordering Platform for Secure Payment Processing: Creating a personalized
online ordering platform will satisfy clients' desires for convenient and frictionless ordering
choices. This platform will provide a user-friendly interface where clients can browse the bakery's
menu, place orders, and make secure online payments. Integration with secure payment
processing systems will give clients confidence in the security of their transactions. Mamma Mia's
Bakery will increase its client base and revenue from online sales by providing this new ordering
channel,
resulting
in
increased
profitability
Centralized
Database
for
Tracking
Sales,
and
Inventory,
market
and
competitiveness.
Customer
Information:
Establishing a centralized database will serve as the backbone of the IT system, enabling
7
comprehensive tracking of sales, inventory, and customer information. This database will contain
transaction data such as sales history, product information, customer profiles, and preferences.
By centralizing this data, Mamma Mia's Bakery will obtain significant insights into purchasing
trends, consumer behavior, and inventory turnover rates. This data-driven strategy will guide
decisions such as menu planning, marketing initiatives, and inventory management methods,
Resulting in increased business growth and profitability. User-Friendly Interface Accessible via
Desktop and Mobile Devices:
A user-friendly interface accessible via desktop and mobile devices will enhance
accessibility and convenience for customers and staff members. This interface will have intuitive
navigation, a visually appealing design, and responsive functioning across multiple devices.
Customers will have a smooth ordering experience, whether they use desktop computers or
mobile devices. Similarly, employees will benefit from having simple access to the POS system
and inventory management tools from anywhere, allowing them to be more flexible and efficient
in their daily operations. This user-friendly design will improve the client experience while
streamlining internal operations, helping Mamma Mia's Bakery succeed.
Project Estimates:
Estimated Project Schedule:
Milestones/Deliverables
Requirements Gathering
System Design
Development and Testing
Implementation and Training
Estimated Project Costs:
Forecasted Completion Date
Month 1
Month 2
Months 3-4
Months 5-6
8
Software: $30,000
Hardware: $15,000
Internal Resources: $10,000
Contractor Resources: $5,000
Total ROM Budget Estimate: $40,000
Primary Stakeholder(s):
Mamma Mia - Owner and Operator
Project Team:
i
Project Manager: Clevin Wiliams
ii
System Designer: Andrew Johnson
iii
Software Developer: Buyole Umuoro
iv
Web Developer: Mwaniki John
v
Inventory Manager: Innesk Ian
vi
Finance Manager: Sharline Joy
Project Constraints and Assumptions:
Constraints:
Budget: $100,000
Timeline: Completion within six months
Limited IT experience and staffing
Assumptions:
Availability of internet connectivity
Cooperation and willingness to learn from Mamma Mia
9
Preliminary Risk Statement:
Risks:
Potential budget overrun
Technical complexities during implementation
Adoption challenges due to lack of IT familiarity
Mitigation Strategies:
Regular budget monitoring
Comprehensive testing and QA processes
Extensive user training and support
Preliminary Communication Plan:
Communication Methods:
Weekly progress meetings with Mamma Mia
Bi-weekly project status reports
Ad-hoc updates via email or phone
Communication Frequency: Weekly
Change Threshold:
Any changes impacting cost, resources, or schedule exceeding 10% require reevaluation
and a new project charter.
Definition of Project Complete:
Project completion is defined by the successful implementation of the IT system, including
operational testing, training, and handover to Mamma Mia's Bakery and Sandwich Shoppe staff.
10
Signatures:
[Clevin Wiliams (manager) sign]
Date: 3/31/2024
[Mamma Mia (client) sign.]
Date: 3/31/2024
11
References.
Noortman, R., Lovei, P., Funk, M., Deckers, E., Wensveen, S., & Eggen, B. (2022).
Breaking up data-enabled design: expanding and scaling up for the clinical
context. Ai Edam, 36, e19.
Bentley, L. D., Dittman, K. C., & Whitten, J. L. (2000). Systems analysis and design
methods. Irwin/McGraw Hill.


Recent Comments