Consider the following table of activities, completion times and predecessors Activity Optimistic Most Likely Pessimistic Predecessor A 5 5 11 B 6 9 12 C 2 3 4 D 3 6 9 A E 3 4 5 B,C F 6 9 12 B G 9...