Project Schedule with Dependency Links
January 2020
Page 1 of 5
Project Fields to Include in ITP Deliverables
Contents
Tasks to include in ITP Deliverables Project Configuration Settings ITP-1 – Project WBS with Durations TTP-3 – Project Schedule with Dependency Links TTP-4 – Project Resources and Costs ITP-3 – Project Risk Assessment TTP-5 – Consolidated Project Management Plan TTP-6 – Project Execution, Tracking and Changes
Tasks to Include in ITP Deliverables
First, before we get to fields – Please make sure that your WBS (and .mpp file) include the following tasks as part of your WBS. Note that this these are necessary but far from sufficient. Many more tasks are needed. This also does not mean that a single task will necessarily suffice for each of these. Rather, include as many tasks as it takes to do the job, but please include at least the following kinds of tasks in addition to whatever else you were planning for your WBS:
Tasks regarding ordering, delivering, and receiving hardware
Tasks regarding ordering, delivering, and receiving software
Tasks regarding ordering, delivering, and receiving networking
Tasks regarding installing hardware
Tasks regarding installing software
Tasks regarding installing networking
Tasks regarding managing, controlling, and monitoring the project and the team
Project meetings To reiterate, there is a lot more to the WBS than this. However, you will find these tasks to be needed in later ITP deliverables. Omitting them would likely be detrimental for many assignments.
January 2020
Page 2 of 5
Project Configuration Settings
Project needs some configuring before you submit these assignments. Hint: This step will count
towards your grade.
NOTE: This is a one-time setup. If you follow the configuration steps for ITP-1, you do not need to
configure Project for later assignments.
Launch Project and open a Blank Project. Open Project Options and adjust your calendar options
settings to look EXACTLY like this:
Verify your scheduling options look EXACTLY like this
Verify your calculation settings look EXACTLY like this
January 2020
Page 3 of 5
ITP-1 Project WBS with Durations
Please ensure that your .mpp file includes at least the following fields (columns) visible in the
left-hand table portion of the Gantt chart view or the Tracking Gantt view:
Indicators (white “i” in a solid blue circle, listed in the Columns list as “Indicators”) [a default field]
Task Mode
Name (i.e., task name) [a default field]
Duration [a default field]
TTP-3 – Project Schedule with Dependency Links
Before we get to TTP-3 fields, a note about the general structure of the TTP-3 schedule: The
Gantt Chart and the Network Diagram should not look like waterfalls, wherein each task has
only one predecessor and only one successor. That is not only unrealistic, but is problematic for
most projects. There should be parallelism. This means that typical tasks should have multiple
successors and/or predecessors.
Please ensure that your .mpp file includes at least the following fields (columns) visible in the
left-hand table portion of the Gantt chart view or the Tracking Gantt view:
All fields from ITP-1
Start date [a default field]
Finish date [a default field]
Predecessors [a default field]
Successors
Additionally, please ensure that the Critical Tasks box in the Format tab is checked.
TTP-4 – Project Resources and Costs
Please ensure that your .mpp file includes at least the following fields (columns) visible in the
left-hand table portion of the Gantt chart view or the Tracking Gantt view and also in the
Resource Sheet view:
All fields from ITP-1 and TTP-3
Resource Name
Material
Type
Group
Standard Rate
Cost per Unit
Cost
Work
January 2020
Page 4 of 5
ITP-3 – Project Risk Assessment
Please ensure that your risk register spreadsheet file includes at least the following fields
(columns):
WBS ID
Task Name or brief description
Task Level (see note in assignment instructions)
Risk Description
Risk Category (Risk Type)
Risk Probability
Risk Consequences (Impact)
Initial Risk Score (Probability * Impact)
Risk Handling Category
Risk Handling/Control Plan
Risk Owner (Risk Manager)
Additional suggested fields:
Est. Cost of Mitigation
Remaining Probability after Mitigation
Remaining Consequences (Impact) after Handling
Final Risk Score
Current Risk Status
Notes and discussion
TTP-5 – Consolidated Project Management Plan
Please ensure that your .mpp file includes at least the following fields (columns) visible in the
left-hand table portion of the Gantt chart view or the Tracking Gantt view:
All fields from ITP-3
TTP-6 – Project Execution, Tracking and Changes
Please ensure that your .mpp file includes at least the following fields (columns) visible in the
left-hand table portion of the Tracking Gantt view:
All fields from TTP-5
Actual Start
Actual Finish
Actual Duration
Baseline Start
Baseline Finish
Baseline Duration
January 2020
Page 5 of 5
On Resource Sheet view:
All fields from TTP-4
Baseline Cost
Additional suggested fields:
Earned Value – EV (BCWP)
PV (BCWS)
AC (ACWP)
Schedule Variance (SV)
Cost Variance (CV)
Estimate at Completion (EAC)
Budget at Completion (BAC)
Schedule Performance Index (SPI)
Cost Performance Index (CPI)
Percent Complete


Recent Comments