BABS Project Management – Assignment 1
Programme: BA Business Studies
Module: Project Management
Module code:
Contribution to 50%
Overall Module
Assessment (%):
Lecturer: Anthony Padovani Internal Verifier:
Assignment Title: Assignment 1: Word count (or 2000
Case Study/individual essay equivalent):
Submission Return date of tba deadline: provisional marks & written feedback:
Submission
All written assessments, where practical and possible, must be submitted via
Turnitin unless otherwise instructed by the Lecturer. (Please DO NOT put this method:
assessment specification into Turnitin or it will match many similarities with other students submissions.)
Alternative submission method (if applicable):
Late submission of the assessment will result in a late penalty mark. Penalties for late submission: Up to one week late, maximum mark of 40%. Over one week late, 0%. Only the Extenuating Circumstances Panel may approve a change to submission dates.
Academic Academic honesty is required. In the main body of your submission you must honesty / give credit to authors on whose research and ideas your work is based. Append referencing: to your submission a reference list that indicates the books, articles, etc. that you have used, cited or quoted in order to complete this assessment.
Module Learning Outcomes (from module syllabus)
1. Understand the primary concepts and practices underpinning Project management
2. Be able to devise and implement a project management plan and work effectively within a
project team.
Page 1 of 10
beyzaranakalebasi
Vurgu
beyzaranakalebasi
Vurgu
TASK DESCRIPTION
BACKGROUND/INTRODUCTION
Planning is an essential activity in many of the complex jobs in business and work organisations of the
modern world. As this complexity increases, the need for systematic planning is much more important
John Ashton, project manager of Megabyte Software, Inc., wants you to prepare a network diagram for their software development project titled Colour Printer Driver Software Project. You will receive a bonus of 100 a day for completing the project earlier than project deadline estimated from critical path. The contract also contains a penalty clause in which you will lose 80 for each day the project takes longer than estimated deadline. The activity time estimates and their dependencies are shown below in the table:
ID Description Predecessor Duration (days)
T01 External specifications None 8
T02 Review Design Features T01 2
T03 Document new features T01 3
T04 Write Software T01 60
T05 Program and test T02 60
T06 Edit and publish notes T03 2
T07 Review Manual T04 2
T08 Alpha site T05, T06 20
T09 Print Manual T07 10
T10 Beta site T08, T09 10
T11 Manufa