I really need help this question:Given EVM data, estimate the cost at completion of a project using the method “EAC based on Continuance of Actual Performance. “BCWS = $82.2MBCWP = $70.5MACWP = $95.5MBAC = $105.5MAssume PMB validity is maintainedAnswers:$124M$143M$153M$164M