For an organization, the following
project schedule is given. Assume that all times are in days.

Task

Predecessor

Normal
Time

Crash
Time

Crash
Cost Slope

A

None

7

7

NA

B

A

3

3

NA

C

A

8

4

600

D

A

4

4

NA

E

B

6

5

600

F

C,
D

2

2

NA

G

E,
F

6

6

NA

H

F

5

3

400

I

G,
H

4

4

NA

J

I

2

2

NA

In a 3- to 4-page Microsoft Word
document, address the following:

Draw the AON project network using
Microsoft Project, Microsoft Visio, or some other tool capable of creating such
a network. Perform a critical path analysis for the network and calculate the
ES, EF, LS, and LF times.

Calculate the slack time for each
activity.

Identify the critical path.

Assume that the organization will
receive a $400 bonus for each day the duration of the project is shortened. The
organization is also responsible for paying the crash cost associated with
shortening the schedule. To maximize the net profit, identify which task you
should crash and by how much.

Support your responses with
examples.
Cite any sources in APA format.
Submission Details

Name your document SU_MGT3059_W2_A2_LastName_FirstInitial.doc.For an organization, the following
project schedule is given. Assume that all times are in days.TaskPredecessorNormal
TimeCrash
TimeCrash
Cost SlopeANone77NABA33NACA84600DA44NAEB65600FC,
D22NAGE,
F66NAHF53400IG,
H44NAJI22NAIn a 3- to 4-page Microsoft Word
document, address the following:
Draw the AON project network using
Microsoft Project, Microsoft Visio, or some other tool capable of creating such
a network. Perform a critical path analysis for the network and calculate the
ES, EF, LS, and LF times.
Calculate the slack time for each
activity.
Identify the critical path.
Assume that the organization will
receive a $400 bonus for each day the duration of the project is shortened. The
organization is also responsible for paying the crash cost associated with
shortening the schedule. To maximize the net profit, identify which task you
should crash and by how much.Support your responses with
examples.Cite any sources in APA format.Submission DetailsName your document SU_MGT3059_W2_A2_LastName_FirstInitial.doc.