At the end of week 10, this project has cost $9,000 and has an earned value as i

At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.Duration (weeks)510152025% CompConceptual Design106100%Graphics Design126430%Copyright4560%Samples420%Tooling6940%Production26140%Total1018222624Cumulative10285076100Select one:a.2.1 b.1.5 c.1.8 d.2.5 At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.Duration (weeks)510152025% CompConceptual Design106100%Graphics Design126430%Copyright4560%Samples420%Tooling6940%Production26140%Total1018222624Cumulative10285076100Select one: