1. The following table defines a project.

1. The following table defines a project.

Activity

Immediate
Predecessors

Activity Time

A

5 days

B

A

9 days

C

A

8 days

D

B

6 days

E

B, C

4 days

F

E

4 days

G

D, F

3 days

The minimum time required to
complete the project is:
A)23
days
B)24
days
C)25
days
D)39
days
E) none of the above

2. Use the network given in the Word file in the Final
Examination Session under Course Content.
The early start time (ES) for job G is:
A) 13
B) 16
C) 21
D) 25
E) 38

3. Use the network given in the Word file in the Final
Examination Session under Course Content.
The late finish time (LF) for job C is
A) 7
B) 14
C) 16
D)21
E) 22

4. Use the network given in the Word file in the Final
Examination Session under Course Content.
The critical path is given by:
A) A ? B ? E ? H
B) A ? B ? F ? H
C) A ? B ? F ? G ? H
D) A ? C ? F ? H
E) A ? C ? F ? G ? H

5. Use
the network given in the Word file in the Final Examination Session under
Course Content.
The minimum time required to complete the project
is:
A)23
days
B)25
days
C)29
days
D)31
days
E) none of the above

6. Use the network given in the Word file in the Final
Examination Session under Course Content.
The slack at activity D is:
A) 0
B) 5
C) 8
D) 13
E) None of the above

7. One part of a PERT project, installing equipment, will most
likely be completed in 6 days. However,
if there are no worker absences, the equipment can be installed in 3 days. If a members the work force happens to catch
Bubonic Flu, this years disease, the installation will take 15 days. What is the expected time (te) for
the equipment installation?
A) 3 days
B) 6 days
C) 7 days
D) 8 days
E) 15 days

8. A firm desires to control inventory levels so as to minimize
the sum of holding and order costs. It
costs the firm $50 to place an order.
The firm estimates its inventory carrying costs at $2/unit/year. Weekly demand is 100 units, and there are 50
weeks in the work year. The item costs
$10 per unit. The lead-time for the
product is 3 weeks. Assume that there
are 5 working days per week.

What
quantity of items should the firm order each time so as to minimize total
inventory costs, i.e., what is the EOQ?
A) 100
B) 224
C) 500
D) 1000
E) none of the above

9. Using the data of Question 8: If 400 units are ordered each
time (i.e., EOQ = 400), then what will be thetotal annual
holding cost?
A) $100
B) $200
C) $400
D) $800
E) $4000

10. Using the data of Question 8: If 200 units are ordered each
time,how many orders will be placed
in a year?
A) 2
B) 5
C) 10
D) 20
E) 25

11. Using the data of Question 8: If 200 units are ordered each
time, then thetime between orders
(in working days) is
A) 2
B) 5
C) 10
D) 20
E) 25

12. Using the data of Question 8: If 1000 are ordered each time,
then what will be thetotal annual order
cost?
A) $50
B) $100
C) $200
D) $250
E) $300

13. Use
the data of Question 8 and assume no safety stock or service level
requirement. In order not to run out of
stock before the receipt of a new order, at what inventory level should the
firm place an order? That is, what is
the reorder point equal to?
A) 50
B) 160
C) 200
D) 300
E) 400

14. Given that unit cost = $25, annual carrying charge = 10%,
annual demand = 7500 units and ordering cost = $15 per order. Assume that there are 50 weeks in the work
year and 5 working days per week. The
lead-time for the product is2weeks.
The EOQ is:
A) 150 units
B) 212.13 units
C) 300 units
D) 500 units
E)none of the above

15. Lincoln Machine Tool Company maintains an inventory pool
consisting of 10 items. Each of these items has a unique demand pattern and may
require a different kind of inventory management system. The annual demand
pattern and the unit cost of these items are given in the following table. Classify the items in A, B, and C categories
according to annual dollar usage.

Annual Usage

Unit Cost

Item Type

in thousands

in Dollars

Item 1

10

$2.50

Item 2

30

$1.25

Item 3

20

$16.00

Item 4

10

$0.75

Item 5

20

$3.00

Item 6

33

$2.50

Item 7

60

$14.25

Item 8

22

$10.00

Item 9

100

$2.75

Item 10

500

$4.25

Using
the above data,Item 7 will be
classified as:
A) A item
B) B item
C) C item
D) None of the above

16. Using the data of Question 15,Item 6 will be classified as:
A) A item
B) B item
C) C item
D) None of the above

17. Using the data of Question 15,Item 8 will be classified as:
A) A item
B) B item
C) C item
D) None of the above

18. One end itemA requires three
component parts:B,C, andD. The bill of material indicates
that for each completedA, 3 units ofB, 2 units ofC,
and 1 unit ofD are required. Current inventory for the four items is as
follows: There are 18As, 40Bs, 50Cs
and 35Ds in stock. If the lead time for all items is one week and
there are no scheduled receipts for any item, how many units of productA
can be delivered to customers at the start of next week (week 2)?
A) 35
B) 31
C)25
D) 13
E) None of the above

Product
D has gross requirements, on-hand inventory, and scheduled receipts as
indicated in the time-phased inventory status record below. Its lead time is 3 weeks.

Item D

1

2

3

4

5

6

Gross Requirements

100

300

100

300

200

50

On Hand/ Scheduled Receipts

700

600

300

200

0

0

Net Requirements

0

0

0

?

200

50

Planned Order Releases

100

?

50

19. The value of entryA
is:
A) 100
B) 200
C) 300
D) 700
E) None of the above.

20. The value of entryB is:
A) 50
B) 200
C) 250
D) 300
E) None of the above

21. Use the BOM given in the Word file in the Final Examination
Session under Course Content. If the
master schedule calls for the production of 50 units ofA, how many units ofE are
needed?
A) 50
B) 100
C) 200
D) 400
E) None of the above

22. Use the BOM given in the Word file in the
Final Examination Session under Course Content. If the
MPS calls for the production of 50 units of itemA, how many units of itemD
are needed?
A) 100
B) 150
C) 300
D) 400
E) None of the above

23. Use the BOM given in the Word file in the
Final Examination Session under Course Content Now assume that 50 units of item
Aare called for by the MPS. On-hand inventory consists of 20 units each
of itemsA,B, D andE. What is the net requirement for itemD?
A) 40
B) 100
C) 120
D) 140
E) 160

24. The
master production schedule for two products, A and B, is shown below. To
manufacture item A, four (4) units of component C are required. To manufacture
item B, three (3) units of component C are required. Using this information,
determine the gross requirements for component C to start week 1.

Master Production Schedule: Wk 1

Product A

30

Product B

25

A) 195
B) 220
C) 155
D) 190
E) None of the above

1. The following table defines a project. ActivityImmediate
PredecessorsActivity TimeA- 5 daysBA 9 daysCA 8 daysDB 6 daysEB, C 4 daysFE 4 daysGD, F 3 days The minimum time required to
complete the project is: A)23
days B)24
days C)25
days D)39
days E) none of the above2. Use the network given in the Word file in the Final
Examination Session under Course Content.
The early start time (ES) for job G is: A) 13 B) 16 C) 21 D) 25 E) 383. Use the network given in the Word file in the Final
Examination Session under Course Content.
The late finish time (LF) for job C is A) 7 B) 14 C) 16 D)21 E) 224. Use the network given in the Word file in the Final
Examination Session under Course Content.
The critical path is given by: A) A ? B ? E ? H B) A ? B ? F ? H C) A ? B ? F ? G ? H D) A ? C ? F ? H E) A ? C ? F ? G ? H5. Use
the network given in the Word file in the Final Examination Session under
Course Content. The minimum time required to complete the project
is: A)23
days B)25
days C)29
days D)31
days E) none of the above6. Use the network given in the Word file in the Final
Examination Session under Course Content.
The slack at activity D is: A) 0 B) 5 C) 8D) 13E) None of the above7. One part of a PERT project, installing equipment, will most
likely be completed in 6 days. However,
if there are no worker absences, the equipment can be installed in 3 days. If a members the work force happens to catch
Bubonic Flu, this years disease, the installation will take 15 days. What is the expected time (te) for
the equipment installation? A) 3 days B) 6 days C) 7 days D) 8 days E) 15 days8. A firm desires to control inventory levels so as to minimize
the sum of holding and order costs. It
costs the firm $50 to place an order.
The firm estimates its inventory carrying costs at $2/unit/year. Weekly demand is 100 units, and there are 50
weeks in the work year. The item costs
$10 per unit. The lead-time for the
product is 3 weeks. Assume that there
are 5 working days per week. What
quantity of items should the firm order each time so as to minimize total
inventory costs, i.e., what is the EOQ? A) 100 B) 224 C) 500 D) 1000 E) none of the above 9. Using the data of Question 8: If 400 units are ordered each
time (i.e., EOQ = 400), then what will be thetotal annual
holding cost? A) $100 B) $200 C) $400 D) $800 E) $4000 10. Using the data of Question 8: If 200 units are ordered each
time,how many orders will be placed
in a year? A) 2 B) 5 C) 10 D) 20 E) 25 11. Using the data of Question 8: If 200 units are ordered each
time, then thetime between orders
(in working days) is A) 2 B) 5 C) 10 D) 20 E) 25 12. Using the data of Question 8: If 1000 are ordered each time,
then what will be thetotal annual order
cost? A) $50 B) $100 C) $200 D) $250 E) $300 13. Use
the data of Question 8 and assume no safety stock or service level
requirement. In order not to run out of
stock before the receipt of a new order, at what inventory level should the
firm place an order? That is, what is
the reorder point equal to?A) 50B) 160C) 200D) 300E) 40014. Given that unit cost = $25, annual carrying charge = 10%,
annual demand = 7500 units and ordering cost = $15 per order. Assume that there are 50 weeks in the work
year and 5 working days per week. The
lead-time for the product is2weeks.
The EOQ is:
A) 150 units
B) 212.13 units
C) 300 units
D) 500 units
E)none of the above15. Lincoln Machine Tool Company maintains an inventory pool
consisting of 10 items. Each of these items has a unique demand pattern and may
require a different kind of inventory management system. The annual demand
pattern and the unit cost of these items are given in the following table. Classify the items in A, B, and C categories
according to annual dollar usage.Annual UsageUnit CostItem Typein thousandsin DollarsItem 110$2.50Item 230$1.25Item 320$16.00Item 410$0.75Item 520$3.00Item 633$2.50Item 760$14.25Item 822$10.00Item 9100$2.75Item 10500$4.25 Using
the above data,Item 7 will be
classified as:A) A itemB) B itemC) C itemD) None of the above16. Using the data of Question 15,Item 6 will be classified as:A) A itemB) B itemC) C itemD) None of the above17. Using the data of Question 15,Item 8 will be classified as:A) A itemB) B itemC) C itemD) None of the above18. One end itemA requires three
component parts:B,C, andD. The bill of material indicates
that for each completedA, 3 units ofB, 2 units ofC,
and 1 unit ofD are required. Current inventory for the four items is as
follows: There are 18As, 40Bs, 50Cs
and 35Ds in stock. If the lead time for all items is one week and
there are no scheduled receipts for any item, how many units of productA
can be delivered to customers at the start of next week (week 2)?A) 35
B) 31
C)25
D) 13
E) None of the above Product
D has gross requirements, on-hand inventory, and scheduled receipts as
indicated in the time-phased inventory status record below. Its lead time is 3 weeks.Item D123456Gross Requirements10030010030020050On Hand/ Scheduled Receipts70060030020000Net Requirements000?20050Planned Order Releases100?5019. The value of entryA
is:A) 100B) 200C) 300D) 700E) None of the above.20. The value of entryB is:A) 50B) 200C) 250D) 300E) None of the above 21. Use the BOM given in the Word file in the Final Examination
Session under Course Content. If the
master schedule calls for the production of 50 units ofA, how many units ofE are
needed?A) 50B) 100C) 200D) 400E) None of the above22. Use the BOM given in the Word file in the
Final Examination Session under Course Content. If the
MPS calls for the production of 50 units of itemA, how many units of itemD
are needed? A) 100B) 150C) 300D) 400E) None of the above23. Use the BOM given in the Word file in the
Final Examination Session under Course Content Now assume that 50 units of item
Aare called for by the MPS. On-hand inventory consists of 20 units each
of itemsA,B, D andE. What is the net requirement for itemD?A) 40B) 100C) 120D) 140E) 16024. The
master production schedule for two products, A and B, is shown below. To
manufacture item A, four (4) units of component C are required. To manufacture
item B, three (3) units of component C are required. Using this information,
determine the gross requirements for component C to start week 1. Master Production Schedule: Wk 1Product A30Product B25A) 195B) 220C) 155D) 190E) None of the above